Permit and Plancheck Items

Go to Interactive Checklist

Permits and planchecks are critical elements in the construction process, ensuring that your project meets all local, state, and federal requirements before, during, and after construction.

This category includes architectural approvals, building permits, specialized permits for different construction phases, and various agency planchecks that need to be obtained throughout your project lifecycle.

Common Permit Types
  • Architectural Planning Board Approval - Initial approval of architectural plans by the local planning board
  • Building Department Permit - Overall construction permit from the building department
  • Demolition Permit - Required before demolishing existing structures
  • Grading Permit - Required for site preparation and earth moving
  • Foundation Permit - Specifically for foundation work
  • Structural Frame Permit - For structural framing work
  • Electrical/Mechanical Permits - Specific to electrical and mechanical installations
Key Considerations
Timing

Some permits must be obtained sequentially, while others can be processed in parallel. Understanding the correct sequence is crucial for project scheduling.

Costs

Permit fees can vary significantly based on project size, location, and complexity. Budget for these costs early in the project planning.

Responsibility

Clearly define which team members or organizations are responsible for obtaining each permit to avoid delays and ensure accountability.

Compliance

Failure to obtain required permits can result in fines, construction delays, or even legal action. Thoroughly review all requirements before starting construction.

Complete List of Permit and Plancheck Items
# Permit/Plancheck Item Description Typical Timeline
1 Architectural Planning Board Approval Initial review and approval of architectural design by local planning authorities 4-8 weeks
2 Filing Fee Administrative fee for filing permit applications Immediate
3 Planning Fee Fee for planning department review Immediate
4 Preliminary Soils Report Assessment of soil conditions for foundation design 2-3 weeks
5 Environmental Fee Fee for environmental impact review Immediate
6 Demolition Permit Permission to demolish existing structures 1-3 weeks
7 Building Department Permit and Plan Check Main construction permit and review of construction plans 4-12 weeks
8 Precise Grading Plan Detailed plan for site grading 2-4 weeks
9 Shoring Permit Required for temporary support of structures during construction 2-4 weeks
10 Grading Permit Permission to alter land elevation and contours 2-6 weeks
11 Foundation Permit Specific permit for foundation construction 2-4 weeks
12 Structural Frame Permit Permit for structural framing work 2-4 weeks
13 Public Improvements Permit Required for work affecting public infrastructure 4-8 weeks
14 OSHPD Plan Check and Permit Office of Statewide Health Planning and Development review (for healthcare facilities) 8-12 weeks
15 ODS Plancheck Office of Design Services review 4-6 weeks
16 ORS Plancheck Office of Regulatory Services review 4-6 weeks
17 Tenant Improvement Permit Required for modifications to existing buildings for tenant use 2-4 weeks
18 Department of Public Works Plancheck Review by Public Works department 3-6 weeks
19 Fire Marshall Plancheck Review of fire safety measures and compliance 2-4 weeks
20 Electrical Plancheck and Permit Review and approval of electrical systems 2-4 weeks
21 Mechanical Plancheck and Permit Review and approval of mechanical systems 2-4 weeks
22 Self-Regulating Agency Plan Check Review by applicable self-regulating agencies Varies
23 State Agency Plancheck Review by relevant state agencies 4-8 weeks
24 Unified School District Authority Approval for projects affecting school districts 3-6 weeks
25 Police Department Approval Review for security and public safety considerations 2-4 weeks
26 Core and Shell Permit Permit for building exterior and structural elements before interior work 3-6 weeks
27 OSHA Permits Occupational Safety and Health Administration compliance 2-4 weeks
28 Tie-back Easement Permission for tie-backs that extend beyond property boundaries 4-8 weeks
29 Encroachment Fee Fee for encroaching on adjacent properties or public right-of-way 2-4 weeks
30 Plan Check Expediting Fee for accelerated plan review Varies
Go to Interactive Checklist