Special Approvals and Requirements

Go to Interactive Checklist

Special approvals and requirements address unique aspects of construction projects that go beyond standard building permits and utility connections.

This category includes environmental permits, community-related fees, specialized approvals, and assessments from various agencies that may be required depending on your project's location, scope, and impact.

Common Special Approval Types
  • Environmental Permits - Requirements related to environmental protection and mitigation
  • Community Impact Fees - Charges to offset project impacts on local communities
  • District Assessments - Fees for special districts (lighting, fire, etc.)
  • Regulatory Agency Approvals - Special permissions from regulatory bodies
  • Design and Aesthetics Reviews - Approvals for visual and aesthetic aspects
  • Special Zone Requirements - Additional requirements for projects in coastal, historical, or other special zones
Key Considerations
Location-Specific

Special approvals often depend on the specific location of your project. Research local requirements early in the planning process.

Extended Timelines

Many special approvals have lengthy review processes. Build adequate time into your project schedule to avoid delays.

Community Engagement

Some special approvals require community outreach or public hearings. Develop a communication strategy to address community concerns.

Documentation

Maintain thorough documentation of all applications, studies, reports, and approvals related to special requirements.

Complete List of Special Approvals and Requirements
# Special Approval/Requirement Description Typical Timeline
1 SWPPP (Storm Water Pollution Prevention) Fee Fee for stormwater management and pollution prevention planning 2-4 weeks
2 AQMD (Air Quality Management District) Approvals related to air quality control during construction 4-8 weeks
3 Community Outreach Plan Plan for engaging with and informing the local community about the project 2-4 weeks
4 Noise Abatement Plan Plan for controlling and mitigating construction noise 2-4 weeks
5 Seismic Survey and Program Fee Costs for seismic evaluations and related programs 4-8 weeks
6 School Assessment and School District Fees Fees paid to school districts to offset impacts of development 2-4 weeks
7 Coastal Development Commission Approval Required for projects in coastal zones 12-24 weeks
8 Parks & Recreation Assessments Fees for impacts on parks and recreational facilities 2-4 weeks
9 Hazardous Abatement Permit and Fee Required for handling hazardous materials during construction 4-8 weeks
10 Environmental Habitat Fees Fees for impacts on natural habitats and ecosystems 4-8 weeks
11 Approval to Work within Utility Easements Permission to work in areas with utility easements 4-8 weeks
12 Acreage Reserve Fees Fees related to water rights and acreage reserves 4-8 weeks
13 Water Quality Board Approvals related to water quality protection 6-12 weeks
14 Handicap Access Fee (ADA) Fees related to Americans with Disabilities Act compliance 2-4 weeks
15 Community Redevelopment Agency Fee Fees for projects in redevelopment zones 4-8 weeks
16 Business License Fee Fees for business licenses related to construction activities 2-4 weeks
17 Mapping Fee Costs for boundary surveys and property mapping 2-4 weeks
18 Planning Commission Process Review and approval by local planning commission 8-12 weeks
19 Design Review Process Aesthetic and design evaluation by local design committee 4-8 weeks
20 Selection Process (Artwork Approval) Approvals for public art components of the project 4-8 weeks
21 Corp. of Engineers Approvals from the U.S. Army Corps of Engineers for projects affecting waterways 12-24 weeks
22 Fire District Assessments Fees paid to fire districts to support fire protection services 2-4 weeks
23 Low Income Housing Assessment Fees to support affordable housing initiatives 2-4 weeks
24 Lighting District Assessment Fees for impact on local lighting districts 2-4 weeks
25 FAA Permit and Assessment Required for structures that might affect air navigation 8-16 weeks
Special Approval Management Strategies
Early Assessment

Conduct a thorough review of all potential special approvals during the pre-planning phase to identify requirements specific to your project.

Expert Consultation

Engage consultants with specific expertise in environmental, regulatory, and community aspects to navigate complex approval processes.

Timeline Management

Create a detailed timeline for all special approvals, working backward from construction milestones to ensure timely submissions.

Stakeholder Engagement

Proactively engage with community stakeholders, regulatory agencies, and other interest groups to address concerns early in the process.

Financial Planning

Create a dedicated budget for special approvals and requirements, including contingency funds for unexpected fees or requirements.

Documentation System

Implement a robust documentation system to track all applications, communications, and approvals related to special requirements.